Module Flow Diagram
BOQ Amendments


NMR Request:
This process is used to define the BOQ (Bill of Quantity) for the job wise. Mapping multiple BOQ with a job can also be done. Based on the BOQ Type selection, the amount will be calculated or entered.
  • If BOQ Type is Item rate, the amount will be calculated based on the item rate multiplied by BOQ quantity.
  • If BOQ Type is Lump Sum, the amount will be entered directly.
  • If BOQ type is Material Supply-Divisible Contract and the process type is Supply BOQ, the amount will be calculated from the Materials Amount.
  • If BOQ type is Material Supply-Divisible Contract and the process type is Service BOQ, the amount will be calculated based on BOQ Service Rate will be multiplied by BOQ quantity
  • If BOQ type is Material Supply-Non Divisible Contract, the amount will be calculated based on the sum of service rate and supply rate will be multiplied by BOQ quantity.

System will capture the following details in the Job Vs BOQ Definition process.

Job Details: Job code and Job name should be given here.

BOQ Details: Here the BOQ name, Process Type, BOQ Type, Quantity, Measurement type, BOQ Rate, BOQ Supply Rate, BOQ Service Rate, Amount and Description will be gathered. BOQ Rate will be taken from the budget against job, based on this value, the amount will be calculated.

Material Details: Material details will be captured, if the Material Supply is divisible Contract and process type is supply BOQ. If Material Supply is divisible Contract and process type is service BOQ, Service Rate and Quantity should be entered. If Material Supply is Non Divisible Contract, then the material details will be captured and Unit Quantity of the Material will also be captured

Structure Mapping Details: If Material Supply is divisible Contract and process type is supply BOQ, then the structure details will be captured in each Material. For all the other BOQ’s, the Structure Quantity will be captured and it should be match with the total BOQ quantity

Eg:

If BOQ type is Item rate -> Amount = BOQ Quantity multiplied by Item rate
If BOQ type is Lump sum -> Amount should be entered
If BOQ Type is material supply - Divisible Contract for supply BOQ -> Amount will be the sum of Materials Amount.
If BOQ Type is material supply - Divisible Contract for Service BOQ -> Amount = (BOQ Quantity*BOQ Service rate)
If BOQ Type is material supply - Non Divisible Contract -> Amount = (BOQ quantity*(Supply Rate + Service Rate)